A Vision To Clear Solutions.
SETTING PROCESS OF CEMENT
Initial & Final
setting Time of cement & concrete
Minimum
thickness of slab is 125 mm.
Water
absorption should not be more than 15 %.
Dimension
tolerance for cubes + – 2 mm.
Compressive
strength of Bricks is 3.5 N /mm2
Maximum
Free fall of concrete allowed is 1.50 m.
In soil
filling as per IS code for every 100 sqm 3 sample for core cutting test should
be taken.
Electrical
conduits shall not run in column
Earth
work excavation for basement above 3 m should be stepped form
Any back
filling shall be compacted 95% of dry density at the optimum moisture content
and in layers not more than 200mm for filling above structure and 300 mm for no
structure
F soling
is specified the soling stones shall be laid at 45° to 60° inclination (and not
vertical) with interstices filled with sand or moorum.
A set of
cube tests shall be carried out for each 30 cum of concrete / each levels of
casting / each batch of cement.
Water cement ratio for
different grades of concrete shall not exceed 0.45 for M20 and above and 0.50 For
M10 / M15 concrete
For
concrete grades M20 and above approved admixture shall be used as per mix
design requirements.
Cement
shall be stored in dry places on a raised platform about 200mm above floor
level and 300mm away from walls. Bags to be stacked not more than 10 bags high
in such a manner that it is adequately protected from moisture and
contamination.
Samples
from fresh concrete shall be taken and at least a set of 6 cubes of 150mm shall
be prepared and cured. 3 Cubes each at 7 days and 28 days shall be tested for
compressive strength. The test results should be submitted to engineer for
approval. If results are unsatisfactory necessary action/rectification/remedial
measures has to be exercised.
Water
used for both mixing and curing shall be clean and free from injurious amounts
of oils, acids, alkalis, salts, sugar and organic materials or other substances
that may be deleterious to concrete or steel. The ph. shall be generally
between 6 and 8.
Cement shall be tested for its setting.
1. The initial setting time shall not be less than 30 minutes.
2. The final setting time shall not be more than 10 hours or 600 minutes
1. The initial setting time shall not be less than 30 minutes.
2. The final setting time shall not be more than 10 hours or 600 minutes
Slump IS 456
Lightly reinforced 25 – 75 mm
heavily reinforced 75 – 100 mm
Trench fill (insitu & Tremie) 100 – 150 mm (For Tremie no need of vibrator)
Lightly reinforced 25 – 75 mm
heavily reinforced 75 – 100 mm
Trench fill (insitu & Tremie) 100 – 150 mm (For Tremie no need of vibrator)
Curing Days Required
Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals and Admixture added cement: 14 days
Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals and Admixture added cement: 14 days
Cube Samples as
per IS-456-2000 Pg. No:29
1 – 5 M3 : 1 No.
6 – 15 M3 : 2 No’s
16 – 30 M3 : 3 No’s
31 – 50 M3 : 4 No’s
Above 50 M3 : 4 + 1 No of addition sample for each 50 M3.
1 – 5 M3 : 1 No.
6 – 15 M3 : 2 No’s
16 – 30 M3 : 3 No’s
31 – 50 M3 : 4 No’s
Above 50 M3 : 4 + 1 No of addition sample for each 50 M3.
SETTING PROCESS OF CEMENT
When water is mixed with cement to form a paste,
reaction starts. In its pure form, the finely ground cement is extremely
sensitive to water. Out of the three main compounds, viz. C3A, C3S and C2S,
reacts quickly with water to produce a jelly-like compound which starts
solidifying. The action of changing from a fluid state to a solid state is
called ‘setting’ and should not be confused with ‘hardening’.
During the next stage of hydration, cement paste
starts hardening owing to the reaction of C3S and C2S with water and the paste
gains strength. The first few minutes, the setting action is more predominant
and later on the hardening action becomes dominant. In practice, such solidifying
action or loss of plasticity is required to be delayed, because some time is
needed for mixing, transporting and placing of concrete into final position
before the mix loses its plasticity due to the setting action.
It is usually specified that the
plastic concrete should be placed and consolidated before initial set has
occurred and it should not then be disturbed until concrete has hardened. This
initial setting time should not be too small and therefore, the standard
specifies minimum initial setting time.Once initial stiffening of concrete has taken
place, it is desirable that it should harden or gain strength as rapidly as
possible, so that there is a minimum of delay before shuttering can be removed
and the risk of frost damage in cold climate is minimized. The standard,
therefore, specifies the maximum value of final setting time.
It is not however, possible in practice to
exactly locate the initial setting time and final setting time. The Indian
Standards have selected two arbitrary points which relate setting of cement to
the time measured from the moment the water is added.
‘Initial setting time’ is defined as the
period elapsing between the time when water is added to the cement and the time
at which the needle of 1 mm square section fails to pierce the test block to a
depth of about 5 mm from the bottom of the mould. A period of
30 minutes is the minimum initial setting time, specified by ISI for
ordinary and rapid hardening Portland cements and 60 minutes for low heat cement.
The ‘final setting time’ is defined as the
period elapsing between the time when water is added to cement and the time at
which the needle of 1 mm square section with 5 mm diameter attachment makes an
impression on the test block . 600 minutes is the
maximum time specified for the final set for all the above mentioned Portland
cements. IS: 269-1976 specifies the strengths in compression on the standard
mortar-cube.
Fig: Vicat Apparatus for
Cement Setting Time Test
Compressive strength test has two functions to
fulfill. Firstly, it is a final check on the quality of cement. Secondly, in
case of doubt, it also helps us to classify the cement as ordinary Portland
cement, rapid hardening Portland cement or low heat Portland cement, according
to the strength it gives after 3 days and 7 days curing.
It is important to note the difference
between setting and hardening of cement at this stage.These compounds contribute very little to the mechanical strength of
concrete, but cement starts losing its plasticity because of loss of water due
to reaction and formation of gel. This loss of plasticity without development
of strength is called setting action.
Cement is said to harden when the cement paste
further reacts with water bringing C2S and C3S into action. These compounds
contribute to the mechanical strength. Hardening, therefore, is associated with
the development of strength.
No comments:
Post a Comment