The following major
topic/points needs to be discuss in any major residential construction project
Sl No
|
ITEMS
DISCUSSED
|
CONCLUSION
|
ACTION
|
TARGET
|
|
01
|
Progress
|
Building Nmae-1 – comments
|
Block work to complete
|
whom
|
Date
|
Sufficient lifting arrangement not
in place. Client observed that the labours are waiting for blocks to lift, to
proceed with work.
|
whom
|
Date
|
|||
Building Nmae-2 – comments
|
EVO to make sure no delay
after. 26thDec 2014.
|
whom
|
Date
|
||
External Works – comments
|
EVO to submit the program
|
whom
|
Date
|
||
Scaffolding- ExternalW2-W5
Scaffolding Material LPO – 25/12
|
whom
|
Date
|
|||
All the external plastering start
|
whom
|
Date
|
|||
Any Additional Substation works
– comments
|
Site area needs to clear
|
whom
|
Date
|
||
Existing cables to avoid and road
network required between building and substation.
|
whom
|
Date
|
|||
Building Works – comments
|
Plastering in progress.Plastering
& internal works – 31st Dec 14
|
whom
|
Date
|
||
Compaction test results
pendingGrade Slab – Concrete
|
whom
|
Date
|
|||
HVAC Works – comments
|
To start
|
whom
|
Date
|
||
Plumbing works- Delay &
pending.
|
Material partially delivered for W1
|
whom
|
Date
|
||
W1 works to complete
|
whom
|
Date
|
|||
02
|
Procurement
management
|
Al. Scaffolding –comments
|
Received 8 set.
|
whom
|
Date
|
Updated procurement schedule
|
With updated status required for
meeting
|
whom
|
Date
|
||
External scaffolding
|
Workers block materials to arrange.
|
whom
|
Date
|
||
03
|
Approval
|
Light fittings-comments
|
To arrange alternative- 2 more system proposal – Ready for submission
|
whom
|
Date
|
Al. Doors & Windows – – Elevation drawing to submitSamples to
arrange
|
2 Supplier conditionally approved.Drwg & Sample awaited.
|
whom
|
Date
|
||
HVAC –comments–
FCU- Pre-insulated
piping- Internal piping
|
Material approval on hold. Clarifications required. ( referred
to main dated 9thDec 14)
|
whom
|
Date
|
||
Door – comments
|
Submitted to consultant
|
whom
|
Date
|
||
Method followed at site – with mortar only, not acceptable.
|
whom
|
Date
|
|||
ACS – Drawing with door location to send
|
whom
|
Date
|
|||
Switches & SocketsMinimum 3 supplier required for review.
|
3 Samples at site. EVO to arrange the sample inspection.
|
whom
|
Date
|
||
Lightening protection – Alternate submission required
|
Letter to arrange it from supplier.
|
whom
|
Date
|
||
Paint Approval
|
Paint system approved- Alternative submittal required.
|
whom
|
Date
|
||
Colour shade to finalize.( Sample paintings required for the based on
provided rendered image)
|
whom
|
Date
|
|||
Ironmongery for steel doors– Clarification on schedule to provide.
|
Sample available and approval meeting to arrange.
|
whom
|
Date
|
||
Heater – Approved but
distribution drawing to submit.
|
FEC approved
|
whom
|
Date
|
||
Responsibility Matrix -comments
|
Quality single point of responsibility
|
whom
|
Date
|
||
Pump set – and any other issues at site work
|
Submission by next week.
|
whom
|
Date
|
||
04
|
Site Management
|
Site external service
drawing- Pending.
|
To submit by 15thDec 14 to consultant
|
whom
|
Date
|
MEP works- inspection to arrange before plastering.( From consultant
& Client)
|
To arrange without any fail. Payment will not be released without
certification from client.
|
whom
|
Date
|
||
Site Layout Drawing
|
Consultant to issue – Forwarded to EVO and to submit for client
approval.
|
whom
|
Date
|
||
Curing – to follow
|
Strictly without fail.
|
whom
|
Date
|
||
Electrical
Works- Daily Report to
send- Quality checks to
be done
|
Noted concerns, on wall chasing, level and filling to be rectified.
|
whom
|
Date
|
||
05
|
Quality
|
3 Observation reports pending to close.
|
EVO to submit immediately.
|
whom
|
Date
|
Quality rectification team to organize
|
To provide different identification and report to generate.
|
whom
|
Date
|
||
Each block to inspect and certify for
clearing the submitted bill.
|
Inspections done, EVO to present it during bill checking
|
whom
|
Date
|
||
All tie rods location needs to be filled with GIC specified compound
|
To provide MAS and to proceed.
|
whom
|
Date
|
||
06
|
Safety
|
Incident report – Pending to close
|
Recommendations to carryout and to submit the report
|
whom
|
Date
|
Site inspection comments Pending to close.
|
To close the
following- Lifting
arrangement.- Other
notes
|
whom
|
Date
|
||
07
|
Labour management
|
STOP eating food at site. All labours must take food from COMO.
|
EVO ensured it & will be strictly followed.
|
whom
|
Date
|
Color coding system to be in place
|
EVO to follow as per safety standards.Helmet & Equipment
|
whom
|
Date
|
||
08
|
Additions
|
Generator proposal to submit:1000KVA, system as communicated.
|
PCT worked out on distribution requirement and will be submitted next
week for review.
|
whom
|
Date
|
Lift for workers block: no action at site. To speed up.
|
Supplier to approve and work to start without affecting other
progress.
|
whom
|
Date
|
||
09
|
Variations
|
All the variation to be submitted by Dec end.
|
To submit
|
whom
|
Date
|
10
|
Billing
|
Site inspections to attach for clearing the submitted bill.
|
To submit.
|
whom
|
Immediately
|
Preliminaries – Status report required
|
To submit-
Mobilization report
pending.- Test
results- Authorities
follow up( No action from contractor)
|
whom
|
Immediately
|
***** End of