M10(1:3.92:5.62)
|
|
Cement
|
210 kg/M3
|
20mm Jelly
|
708 Kg/ M3
|
12.5mm Jelly
|
472 Kg/M3
|
River Sand
|
823 kg/M3
|
Total Water
|
185 Kg/M3
|
Fresh Concrete density
|
2398 Kg /M3
|
M20(1:2.48:3.55)
|
|
Cement
|
320 kg/M3
|
20mm Jelly
|
683 Kg/ M3
|
12.5mm Jelly
|
455 Kg/M3
|
River Sand
|
794 kg/M3
|
Total Water
|
176 Kg/M3
|
Admixture
|
0.70%
|
Fresh Concrete density
|
2430 Kg /M3
|
M25(1:2.28:3.27)
|
|
Cement
|
340 kg/M3
|
20mm Jelly
|
667 Kg/ M3
|
12.5mm Jelly
|
445 Kg/M3
|
River Sand
|
775 kg/M3
|
Total Water
|
185 Kg/M3
|
Admixture
|
0.60%
|
Fresh Concrete density
|
2414 Kg /M3
|
Note:Sand 775+2% Moisture,Water
185-20.5=164 Litres,
|
|
Admixture=0.5 % is 100ml
|
|
M30(1:2:2.87)
|
|
Cement
|
380 kg/M3
|
20mm Jelly
|
654 Kg/ M3
|
12.5mm Jelly
|
436 Kg/M3
|
River Sand
|
760 kg/M3
|
Total Water
|
187 Kg/M3
|
Admixture
|
0.70%
|
Fresh Concrete density
|
2420 Kg /M3
|
Note:Sand =760 Kg with 2% Moisture
(170.80+15.20)
|
|
M35(1:1.79:2.57)
|
|
Cement
|
410 kg/M3
|
20mm Jelly
|
632 Kg/ M3
|
12.5mm Jelly
|
421 Kg/M3
|
River Sand
|
735 kg/M3
|
Total Water
|
200 Kg/M3
|
Admixture
|
0.70%
|
Fresh Concrete density
|
2400 Kg /M3
|
Note:Sand
=735+2%,Water=200-14.7=185.30
|
|
Admixture=0.7%
|
|
M40(1:1.67:2.39)
|
|
Cement
|
430 kg/M3
|
20mm Jelly
|
618 Kg/ M3
|
12.5mm Jelly
|
412 Kg/M3
|
River Sand
|
718 kg/M3
|
Water cement ratio
|
0.43
|
Admixture
|
0.70%
|
Note:Sand =718+Bulkage 1%
|
|
M45(1:1.58:2.26)
|
|
Cement
|
450 kg/M3
|
20mm Jelly
|
626 Kg/ M3
|
12.5mm Jelly
|
417 Kg/M3
|
River Sand
|
727 kg/M3+Bulkage 1%
|
Water cement ratio
|
0.43
|
Admixture
|
0.70%
|
M50(1:1.44:2.23)
|
|
Cement
|
450 kg/M3
|
20mm Jelly
|
590 Kg/ M3
|
12.5mm Jelly
|
483 Kg/M3
|
River Sand
|
689 kg/M3+Bulkage 12%
|
Water cement ratio
|
0.36 (188 Kg)
|
Admixture
|
1.20%
|
Micro Silica
|
30 Kg
|
Super Flow
|
6.7 % of cement
|
Design Mix Started from M20..